
2026 Realistic Verified Free Medical Professional CCM Exam Questions
CCM Real Exam Questions and Answers FREE
NEW QUESTION # 23
Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?
- A. Red Book
- B. Yellow Book
- C. Silver Book
- D. Yellow or Silver Book
Answer: A
Explanation:
The FIDIC Red Book (2017 edition) is traditionally used for construction contracts where the Employer provides the design, and the Contractor primarily executes the construction works. This form is suitable for Employers who have detailed and well-defined design and engineering requirements and want to retain control over the design.
* TheRed Bookis ideal for experienced Employers who have a clear and fixed design and require the Contractor to build accordingly.
* TheYellow Bookis typically used where the Contractor is responsible for both design and construction (design & build). It suits Employers who want to delegate design responsibility to the Contractor.
* TheSilver Bookis used for turnkey or EPC contracts where the Contractor takes full responsibility for design, procurement, construction, and commissioning, suitable for Employers seeking minimal involvement in design and execution details.
* Hence, for an Employer whoknows exactly what they wantfrom a design and engineering perspective and wants to maintain control, theRed Bookis the first and most appropriate choice.
References:
FIDIC Red Book 2017 Edition - Conditions of Contract for Construction
FIDIC Yellow Book 2017 Edition - Conditions of Contract for Plant and Design-Build FIDIC Silver Book 2017 Edition - Conditions of Contract for EPC/Turnkey Projects FIDIC Contract Manager Study Guide, Module on Contract Selection
NEW QUESTION # 24
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
- A. True
- B. False
Answer: B
Explanation:
Comprehensive and Detailed Explanation:
The Contractor may submit Value Engineering proposals to improve efficiency or reduce costs; however, it is not an absolute contractual obligation to submit such proposals. Also, the preparation of these proposals is generally at the Contractor's own cost initially. If the proposal is accepted and results in a Variation, then adjustments to the Contract Price may occur, potentially reimbursing the Contractor.
Thus, both statements are false.
References:
FIDIC Red, Yellow, Silver Books 1999 & 2017 Editions, Sub-Clause 13.1 - Value Engineering FIDIC Contract Manager Study Guide, Module on Variations and Value Engineering
NEW QUESTION # 25
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
- A. In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.
- B. There is never a difference in effect whether in the Particular Conditions when the term "Works" is used, or when the term "works" is used.
- C. Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.
- D. Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.
Answer: A,D
Explanation:
Comprehensive and Detailed Explanation:
Option B is correct: The Contract Data provides information required by specific Sub-Clauses in the General Conditions to complete the contract.
Option D is correct: If required data is missing in the Contract Data, some Sub-Clauses may not apply.
Option A is incorrect; definitions generally apply throughout the contract including Specifications and Drawings.
Option C is incorrect; case sensitivity of terms can affect contractual meaning.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 1.1 - Definitions and Contract Data FIDIC Contract Manager Study Guide, Module on Contract Documents
NEW QUESTION # 26
The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?
Choose all of the correct answers (multiple possibilities).
- A. If advance payment is not completely repaid before the Performance Certificate is issued.
- B. If the advance payment is not completely repaid before termination of the Contract.
- C. If the advance payment is not completely repaid before the Taking-Over Certificate is issued.
- D. If the advance payment is not completely repaid before Time for Completion.
Answer: B,D
Explanation:
Under the FIDIC Red Book 1999, advance payment is a sum paid to the Contractor to help cash flow early in the project. It must be repaid through deductions from interim payments according to a specified schedule.
* Sub-Clause 14.5 (Advance Payment)states that the Contractor must repay the advance payment by installments, typically by the Time for Completion. If the advance payment has not been fully repaid by the Time for Completion, the outstanding balance becomes immediately due and payable by the Contractor (Option A). This ensures the Employer recovers the advance by the time the project completes.
* Additionally,upon termination of the Contract(Sub-Clause 15.2 or relevant termination clauses), any outstanding balance of the advance payment becomes immediately due (Option D). This protects the Employer's financial interest if the Contract ends prematurely.
* Option B (before the Performance Certificate is issued) and Option C (before the Taking-Over Certificate is issued) arenotexplicitly linked in FIDIC Red Book 1999 to triggering immediate repayment of the advance payment. The Taking-Over Certificate marks practical completion and may precede the final repayment schedule, while the Performance Certificate is issued after the Defects Notification Period.
Therefore, the correct situations for immediate repayment of outstanding advance payment balance arebefore Time for Completion and upon termination of the Contract.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 14.5 - Advance Payment
FIDIC Red Book 1999 Edition, Sub-Clause 15.2 - Termination by Employer (Payment obligations) FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 27
There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.
Which two of the following statements areNOTapplicable reasons?
(Choose all correct answers - multiple possibilities)
- A. Increase the performance of the Works when completed.
- B. Delay the execution of the Works or a Section.
- C. Decrease the Contract Price.
- D. Adversely affect the work of the Contractor's Personnel.
Answer: A,C
Explanation:
Comprehensive and Detailed Explanation:
Under the FIDIC Red Book 2017 (similar principles apply in other editions), Sub-Clause 4.1 ("Contractor's General Obligations") and Sub-Clause 3.4 ("Delay Damages") require both Employer and Contractor to notify the Engineer in advance about any events or circumstances which maydelay the worksoradversely affect the Contractor's personnel or progress. This early notification ensures proper management and mitigation of risks that could impact the project timeline or quality.
* Option A (Delay the execution of the Works or a Section)is a core reason for notification since delays affect the critical path and programme, requiring possible extensions or adjustments.
* Option C (Adversely affect the work of the Contractor's Personnel)is also a valid reason because issues affecting workforce productivity or availability can impact project delivery.
On the other hand:
* Option B (Decrease the Contract Price)isnota reason to notify. Changes in contract price usually arise from variations or claims but are not a "known or future event" requiring prior notification unless linked to a variation or compensation event.
* Option D (Increase the performance of the Works when completed)is positive and does not negatively affect project progress or cost; therefore, it is not a reason for advance notification under these contract provisions.
Thus, the twonot applicablereasons are B and D.
References:
FIDIC Conditions of Contract for Construction, 2017 Edition, Sub-Clause 4.1 - Contractor's General Obligations FIDIC Conditions of Contract for Construction, 2017 Edition, Sub-Clause 3.4 - Delay Damages FIDIC Contract Manager Study Guide, Module on Communication and Reporting
NEW QUESTION # 28
Which one of the following statements is correct regarding the Employer's Representative under the FIDIC Silver Book (edition 1999)?
- A. The Employer may appoint an Employer's Representative to act on his behalf under the Contract.
- B. The Employer must always appoint an Employer's Representative to act on his behalf under the Contract.
- C. The Representatives of both the Employer and the Engineer have no authority to amend the Contract at all.
- D. The Employer may appoint an Employer's Representative to act on his behalf under the Contract but has to consult the Contractor to agree to this Representative.
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
Under the FIDIC Silver Book (1999 edition), the Employer may appoint an Employer's Representative to act on their behalf, but this is discretionary and not mandatory (Option B). The Employer's Representative acts within the authority delegated by the Employer but cannot amend the Contract unless expressly authorized.
Option A is partly correct but less complete than B.
Option C is incorrect; the appointment is not compulsory.
Option D is incorrect; the Employer is not contractually obliged to consult the Contractor for appointment approval.
References:
FIDIC Silver Book 1999 Edition, Clause 1.1 and Clause 3 - Employer's Representative FIDIC Contract Manager Study Guide, Module on Contract Administration
NEW QUESTION # 29
In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:
"In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction." What GP(s) is/are breached?
- A. GP1 only
- B. GP1 and GP3
- C. GP3 only
- D. GP1, GP2 and GP3
Answer: B
Explanation:
This clause breaches Golden Principles (GP) 1 and 3:
GP1 promotes fairness and balanced risk allocation between parties. Forcing the Contractor to carry out determinations despite a notice of dissatisfaction undermines fair dispute resolution and contractual balance.
GP3 emphasizes the importance of clear and unambiguous contract drafting that reflects agreed procedures.
This sentence introduces ambiguity and overrides contractual rights to dispute determinations.
References:
FIDIC Contract Management Guidelines - Golden Principles
FIDIC Contract Manager Study Guide, Module on Contract Administration and Contract Clauses
NEW QUESTION # 30
Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
- A. The DAB Decision is final and binding
- B. Deletion of Sub-Clauses 20.2 - 20.4 for a Project constructed in United Arab Emirates
- C. The Payment shall be released by the Employer within 180 days calculated from receiving the Contractor's Monthly Statement
- D. The Contractor is responsible for the performance of the Nominated Subcontractors
Answer: B,C
Explanation:
Option B is correct: Deleting critical dispute resolution Sub-Clauses 20.2 - 20.4 contradicts the Golden Principles by undermining fair dispute handling.
Option D is correct: Extending payment release to 180 days violates timely payment principles and fairness in cash flow management.
Option A is generally acceptable as the Contractor often assumes responsibility for nominated subcontractors.
Option C is acceptable in some jurisdictions and contracts to provide finality but can be debated.
References:
FIDIC Contract Management Guidelines - Golden Principles
FIDIC Red Book 1999 Edition, Clauses 20 and 14
NEW QUESTION # 31
Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?
- A. The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor's failure to comply with the notice requirements.
- B. It is the Employer's Representative who must first respond to the claim by the Contractor.
- C. The Engineer's response to a claim by the Contractor is final and binding upon the Employer.
- D. If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.
- E. The Engineer's response to the Contractor's submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer's final decision on the quantum.
Answer: D
Explanation:
Under FIDIC Red Book 1999, the Engineer plays a key role in determining claims submitted by the Contractor (Clause 20). If the Engineer fails to make a determination within the prescribed time, the Parties may be unable to resolve the dispute and thus the matter may proceed to dispute resolution mechanisms.
Option B is correct because if the Engineer does not decide, the claim remains unsettled, and the Parties are left to resolve the dispute, often via Dispute Adjudication Board or arbitration.
Option A is incorrect; claims must comply with notice requirements to be valid.
Option C is incorrect because the Engineer may request further particulars but is not obligated to give a final decision on quantum immediately.
Option D is incorrect as the Engineer, not the Employer's Representative, first responds to claims.
Option E is incorrect since the Engineer's decision is not final and binding if disputed; it may be challenged.
References:
FIDIC Red Book 1999 Edition, Clause 20 - Claims, Disputes and Arbitration FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution
NEW QUESTION # 32
Regarding the FIDIC Red Book (edition 1999), which two statements are true?
- A. In emergency situations notices can also be submitted verbally (rather than (also) in writing).
- B. A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.
- C. A notice is to be signed by the Engineer, Contractor's Representative or Employer's Authorised Representative.
- D. Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.
Answer: A,D
Explanation:
Comprehensive and Detailed Explanation:
Option A is true: In emergencies, verbal notices are permitted with the requirement to follow up in writing.
Option D is true: Notices and communications may be sent in various formats including handwritten, typed, printed, or electronic systems.
Option B is incorrect; a notice does not necessarily have to be signed by all these representatives; it depends on the party issuing the notice.
Option C is incorrect; proof of receipt is ideal but not always strictly required for legal validity depending on contract provisions.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 1.3 - Communications and Notices FIDIC Contract Manager Study Guide, Module on Contract Communication
NEW QUESTION # 33
You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".
For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for
200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.
In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m.
However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding.
The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.
As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.
In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?
- A. The Contractor is entitled to both Claims.
- B. The Contractor is not entitled to either of the Claims.
- C. The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.
- D. The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.
Answer: A
Explanation:
Both claims are valid under the Silver Book principles:
The error in the Employer's Requirements (typo in NTS-PW-01) leads to entitlement for additional piling costs.
The unforeseen hydrological data causing additional flood protection works qualify as unforeseeable physical conditions entitling the Contractor to compensation.
Hence, Option D is correct - the Contractor is entitled to both claims.
References:
FIDIC Silver Book 2017 Edition, Sub-Clause 4.1 (Employer's Requirements) and Sub-Clause 4.12 (Unforeseeable Physical Conditions) FIDIC Contract Manager Study Guide, Module on Claims and Employer's Requirements
NEW QUESTION # 34
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
- A. In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.
- B. Both 'Disagreement' and 'Dispute' are defined terms under the Conditions of Contract.
- C. The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.
- D. If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub- Clause 21.4 to obtain a DAAB decision on it.
Answer: A,D
Explanation:
Option A is correct. Under Sub-Clause 11.9 (Performance Certificate) refusal or incorrect issuance by the Engineer, combined with disagreement by the Contractor, may cause a Dispute to arise.
Option B is correct. If a Party is dissatisfied with a determination, it must give a Notice of Dissatisfaction (NOD) within 28 days to escalate the matter to a Dispute, allowing either Party to refer it to the DAAB as per Sub-Clause 21.4.
Option C is incorrect. The contract does not specify a 42-day time limit for submission to DAAB after NOD; timelines vary by contract and stage.
Option D is incorrect. 'Disagreement' is not a formally defined term in FIDIC contracts, whereas 'Dispute' is.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 11.9 and Clause 21 - Claims, Disputes, and Adjudication FIDIC Contract Manager Study Guide, Module on Dispute Resolution
NEW QUESTION # 35
Choose which one statement consists of an example of an unclear and ambiguously drafted Particular Conditions.
- A. All deletions of a General Conditions are replaced with new Particular Conditions that cover the same scope.
- B. Provisions of the General Conditions are deleted and replaced in the Particular Conditions solely by the words "not used".
- C. The clarifications to the Contract given during the tender period are never to be attached to the Contract, as such clarifications are reflected by amending the Particular Conditions.
- D. Clarifications to the meaning of tender documents together with answers to tenderers' inquiries made during the tender period by the Employer should be e-mailed in a Excel table in both PDF and XLS file format.
Answer: B
Explanation:
The use of vague phrases such as "not used" in Particular Conditions to delete provisions of the General Conditions without replacement or explanation leads to ambiguity and unclear contractual obligations. Such drafting can cause confusion as it fails to clarify whether the deleted provisions are simply not applicable or replaced by other terms. This practice is discouraged because it creates legal uncertainty and possible disputes regarding the rights and responsibilities of the parties.
Option A exemplifies this problem, as it deletes General Conditions clauses without specifying alternatives or clarifications.
Option B is a good practice where deletions are replaced by well-defined clauses to maintain contract balance.
Option C describes a clear method of issuing clarifications, promoting transparency and traceability.
Option D is consistent with standard practice, where clarifications during tender are formalized by contract amendments.
References:
FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures and Particular Conditions drafting FIDIC Red Book 2017 Guide notes on drafting Particular Conditions
NEW QUESTION # 36
Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer's prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer's prior approval or not. Is this statement true or false?
- A. True
- B. False
Answer: B
Explanation:
Under the FIDIC Red and Yellow Books 1999 editions, the Engineer acts as the Employer's representative with authority delegated under the contract. When an instruction requires the Employer's prior approval, it is primarily the Engineer's responsibility to obtain that approval before issuing the instruction to the Contractor.
The Contractor isnot contractually required to verifywhether the Engineer has obtained the Employer's approval. The Contractor is generally entitled to rely on the Engineer's instructions as valid and binding unless there is clear evidence to the contrary.
This principle avoids placing an undue administrative burden on the Contractor and maintains the hierarchical contract administration structure, where the Engineer is the primary point of contact and decision-maker.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 3.1 - Engineer's Duties and Authority FIDIC Yellow Book 1999 Edition, similar provisions FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures
NEW QUESTION # 37
In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?
- A. In case of large scale works, where there are several companies likely to have an interest in submitting an offer.
- B. When there is a limited number of capable experienced contractors available and ready to take part in the procurement.
- C. If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.
- D. When the works are simple and of short duration.
Answer: A
Explanation:
Two-stage procurement, involving pre-qualification followed by tender, is typically recommended for large- scale projects where many potential contractors might be interested. This process helps to shortlist qualified contractors, thus streamlining the tender evaluation and increasing the quality and competitiveness of submitted offers.
Option C correctly reflects this approach for complex or large projects where competition needs to be managed.
Option A is incorrect since simple, short-duration projects usually do not require complex procurement.
Option B is incorrect because if only a few capable contractors exist, pre-qualification may be less necessary.
Option D is incorrect as international financing does not always mandate two-stage procurement, although it often influences procurement methods.
References:
FIDIC Contract Manager Study Guide, Module on Contract Formation and Procurement Strategies World Bank Procurement Guidelines and Common Industry Practice
NEW QUESTION # 38
Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)
- A. No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.
- B. No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause
7.4. - C. Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor's Documents in the Employer's Requirements, as stated in Sub-Clause 5.2.
- D. Yes, because otherwise the Contractor doesn't have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.
Answer: C
Explanation:
Under the FIDIC Silver Book 1999 (Conditions of Contract for EPC/Turnkey Projects), the Employer must specify clearly in the Employer's Requirements which Contractor's Documents are to be submitted. Sub- Clause 5.2 states that the Contractor must submit all documents listed in the Employer's Requirements, ensuring clarity and enabling the Employer to control the documentation process.
Option D is correct because it highlights the need for Employer's Requirements to define the scope and content of the Contractor's Documents.
Option A is incorrect; although operation and maintenance manuals are generally required, they are part of the specified Contractor's Documents, not automatically required without Employer's direction.
Option B is incorrect as the Contractor's duty to supply documents is limited to those specified.
Option C is incorrect because documentation obligations are ongoing and not just at completion.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 5.2 - Contractor's Documents FIDIC Silver Book 1999 Edition, Sub-Clause 1.8 - Time for Completion FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures
NEW QUESTION # 39
The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition
1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back- to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
"Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause
5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
- A. I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.
- B. I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer's Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even without SC having the opportunity to review it.
- C. I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer's Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to Contractor, the SC can accept this risk and enter into the subcontract.
- D. I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.
Answer: B
Explanation:
In FIDIC Yellow Book (1999), the Contractor is responsible for scrutinizing the Employer's Requirements per Sub-Clause 5.1 and must notify any discrepancies or errors. However, passing this obligation to a Subcontractor, and requiring the Subcontractor to indemnify the Contractor for errors or defects arising from the Employer's Requirements or the Contractor's design, unfairly shifts risk and liability to the Subcontractor.
The Subcontractor is likely not in a position to fully review or control the Employer's Requirements or the overall Contractor's design. This exposes the Subcontractor to excessive risk, beyond their scope and capacity.
Advice C highlights that the Subcontractor becomes vulnerable to claims for design defects outside their control. This misallocation of risk is generally not recommended and can be challenged during contract negotiation. Good contract management practice and risk allocation principles (FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution) support this position.
While Options A, B, and D propose different approaches, only C correctly identifies the fundamental contractual and risk management issue that should prevent the Subcontractor from entering the contract as is.
References:
FIDIC Yellow Book 1999, Sub-Clause 5.1 - Contractor's General Obligations FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution FIDIC Contract Manager Study Guide, Module on Risk Management
NEW QUESTION # 40
The procurement process of a project executed based on any FIDIC Contract model is exactly the same in terms of definitions, time and steps, which makes it universal and more easy to use worldwide. Is this statement true or false?
- A. True
- B. False
Answer: B
Explanation:
This statement is false. While FIDIC Contracts provide standardized contractual frameworks, procurement processes vary widely depending on local laws, employer requirements, contract editions, and project specifics. Definitions, timelines, and procurement steps may differ between models and jurisdictions, making the procurement process not universally identical.
The FIDIC contracts are adaptable tools, not rigid procurement procedures, so users must tailor procurement to local and project needs.
References:
FIDIC Contract Manager Study Guide, Module on Contract Formation and Procurement Strategies Various National Procurement Regulations and Practices
NEW QUESTION # 41
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor's Proposal. Which two of the following statements are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).
- A. The Contractor is entitled to change the design by optimising the design, without approval of the Employer/Engineer.
- B. The Contractor is not allowed to make any changes regarding the design to optimise the design, unless approved by the Engineer/Employer.
- C. The Contractor is not allowed to submit a proposal for Value Engineering, as any value engineering should already have taken place before submitting its design proposal.
- D. The Contractor may submit a proposal for Value Engineering.
Answer: B,D
Explanation:
Option B is correct: The Contractor must obtain approval from the Engineer/Employer before making design changes.
Option C is correct: The Contractor can submit Value Engineering proposals to improve efficiency or reduce costs.
Option A is incorrect; unilateral changes are not allowed.
Option D is incorrect; Value Engineering can be proposed even after initial submission.
References:
FIDIC Yellow and Silver Books 1999 Edition, Sub-Clauses 4.1 and 4.4
FIDIC Contract Manager Study Guide, Module on Design and Value Engineering
NEW QUESTION # 42
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
- A. 12 June 2022
- B. 15 July 2022
- C. 15 June 2022
- D. 1 August 2022
Answer: D
Explanation:
According to the FIDIC Yellow Book 2017, the Commencement Date is the date notified by the Engineer as the date on which the Contractor shall start the execution of the Works (Sub-Clause 8.1). In this case, although the Engineer notified 15 July 2022 as the Commencement Date, it was subject to the issuance of the construction permit. Since the construction permit was only obtained on 1 August 2022, work could not legally commence before that date.
FIDIC recognizes that the Contractor cannot be expected to start before all necessary permissions are granted.
Hence, the effective Commencement Date must be the earliest date on which the Contractor can legally commence work, i.e., the date when the permit was issued (1 August 2022). The contract's requirement that the Commencement Date notification occur no later than 14 days after signing is subject to actual readiness conditions (permit availability).
Therefore, for purposes of delay and completion, the Commencement Date is 1 August 2022. This affects the calculation of the Time for Completion and any delay claims accordingly.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 8.1 - Commencement of Works
FIDIC Yellow Book 2017 Edition, Sub-Clause 2.1 - Right of Access to Site and Permits FIDIC Contract Manager Study Guide, Module on Contract Formation and Execution
NEW QUESTION # 43
......
Exam Dumps CCM Practice Free Latest Medical Professional Practice Tests: https://www.lead2passed.com/Medical-Professional/CCM-practice-exam-dumps.html
CCM Exam Questions | Real CCM Practice Dumps: https://drive.google.com/open?id=1PoBHcyiikqgMUucAv2o4vceTK86MJ45d