NEW QUESTION 70
What are the core capabilities in SAP Cloud ALM for operations? Note: There are 3 correct Answers to this question.
- A. Event and alert management
- B. Upgrade analysis
- C. Operation automation
- D. Monitoring
- E. License management
Answer: A,C,D
NEW QUESTION 71
How can the project manager help to keep momentum in the project and help to keep the customer involved?
- A. Walk through the solution processes with the stakeholders
- B. Add customer resources to the project to reduce the need for formal training
- C. Leverage agile cycles to build and test the solution
- D. Increase the number of Q-Gates
Answer: B,C
NEW QUESTION 72
What are the enablement areas relevant for all Customer Team members coming from the Business?
- A. Technical expertise
- B. Project management
- C. Solution expertise
- D. Workstream enablement
Answer: A,B,C
NEW QUESTION 73
Implementation of which solutions are supported by the SAP Activate Framework?
- A. C4C
- B. SAP S/4HANA On-Premise
- C. SAP S/4HANA Cloud
- D. BW/4HANA On-Premise
- E. SAP SuccessFactors
Answer: A,B,C,D,E
NEW QUESTION 74
What is the minimum number of quality gates mandated by the SAP Activate methodology?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 75
What does "de-coupling extensions" mean in SAP S/4HANA Cloud?
- A. Extensions are applied with modifications in the HANA database
- B. Extensions will not clash with quarterly release upgrades
- C. Extensions could conflict with future release enhancements
- D. Extensions are separated from the stable system of records
Answer: D
NEW QUESTION 76
SAP Solution Manager is the default ALM solution for SAP S/4HANA On-Premise implementation scenarios. If it is used in the project then artifact "Solution Manager Design Document" shall be developed during Prepare phase.
- A. True
- B. False
Answer: A
NEW QUESTION 77
What do you do during an iterative approach to build a solution? Please choose the answer.
- A. Include frequent inspection check-points
- B. Deliver a prototype of the solution
- C. Build the solution module by module
- D. Provide a working solution only at the end of the release
Answer: A
NEW QUESTION 78
Which of the following is part of the Explore phase in the "New implementation od SAP S/4 HANA Cloud" transition path?
- A. Simplification and custom code impact analysis
- B. Solution validation and Delta design
- C. Fit-to-standard
- D. Setup and enablement
Answer: C
NEW QUESTION 79
Your are defining the test strategy for your project. What would you include in a Scope of Integration test?
- A. the connectivity between database and application servers
- B. the functionality of end-to-end business processes
- C. the network communication
- D. the functionality of modular processess
Answer: B
NEW QUESTION 80
What does SAP Activate recommend to keep team members informed and aligned?
- A. Daily team stand-up meeting
- B. Daily e-mail status updates to project manager
- C. Daily progress review meeting with sponsor
- D. Daily status meeting with project manager
Answer: A
NEW QUESTION 81
Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct Answers to this question.
- A. Project Plan
- B. Change Management Roadmap
- C. End User Learning Needs Analysis
- D. Detailed Design - Business Process
- E. Learning Content
Answer: B,C,E
NEW QUESTION 82
What is the key difference between Notes and Requirements in the Change and Deploy capability of SAP Cloud ALM?
- A. Notes are created from tasks
- B. Users can create a follow-up task that is actionable for Requirements
- C. Users can create a follow-up task that is actionable for Notes
- D. Requirements are created from tasks
Answer: D
NEW QUESTION 83
What are some of the key topics covered in the Customer Team Enablement workstream? 3 correct answers
- A. solution expertise
- B. planning skills
- C. technical expertise
- D. project management
- E. project sourcing approach
Answer: A,C,D
NEW QUESTION 84
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the answer.
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: C
NEW QUESTION 85
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the answer.
- A. Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity
- B. Relative estimate in ideal person days that reflects the best estimate provided by the project team
- C. Product Owner's relative estimate of the effort that will be needed to implement the user story
- D. Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks
Answer: C
NEW QUESTION 86
......