SAP C-TS410-1809 Exam Syllabus Topics:

TopicDetails
Topic 2
  • Describe the business process of enterprise asset management
  • Explain the project system capabilities
Topic 3
  • Describe human capital management functionalities and the integration scenarios with Success Factors
  • Enterprise Asset Management
Topic 4
  • Role of SAP Fiori UX and the concept of organizational structures and master data
  • Core Finance: Management Accounting (CO)
Topic 5
  • Describe warehouse management functionalities
  • Describe the functionalities of financial accounting
Topic 6
  • Explain the order to cash business process
  • Human Capital Management
  • Purchase to Pay Processing
Topic 7
  • Plan to Produce Processing
  • Order to Cash Processing
  • Describe SAP S/4HANA as an enabler for digital transformation
Topic 8
  • Describe the functionalities of management accounting
  • Explain the purchase to pay business process
Topic 9
  • Explain the plan to produce business process
  • Core Finance: Financial Accounting (FI)

 

NEW QUESTION 14
Which documents are created when you post a valuated goods receipt for consumable materials?
There are TWO correct answers for this Question
Response:

  • A. Accounting document
  • B. Sales order document
  • C. Vendor invoice document
  • D. Controlling document

Answer: A,D

 

NEW QUESTION 15
Which of the following functions can result in a creation of reservations for a production order?
There are 2 correct answers to this question.
Response:

  • A. Record manufacturing activities
  • B. Convert planned order to production order
  • C. Release production order
  • D. Calculate production cost

Answer: B,C

 

NEW QUESTION 16
What are the key technologies that enabled the development of SAP S/4HANA?
There are TWO correct answers for this Question
Response:

  • A. Multicore central processing units
  • B. Mobile devices
  • C. Large memory capacities
  • D. Fast wireless networking

Answer: A,C

 

NEW QUESTION 17
What is required to report on a combination of characteristics, such as customer, product, and region?
Response:

  • A. G/L accounts
  • B. Profitability segments
  • C. Profit centers
  • D. Primary cost elements

Answer: B

 

NEW QUESTION 18
In what step of the purchase-to-pay process is a purchase requisition generated?
Response:

  • A. Invoice verification
  • B. Source of supply determination
  • C. Determination of requirements
  • D. Vendor selection

Answer: C

 

NEW QUESTION 19
In your warehouse, you want to ensure that material is putaway in the ideal bin to improve efficiency.
What SAP Extended Warehouse Management feature do you implement?
Response:

  • A. Slotting/rearrangement
  • B. Cross-docking
  • C. Yard management
  • D. Wave management

Answer: A

 

NEW QUESTION 20
Which of the following is a feature of Streamlined Procurement?
Response:

  • A. Self-service requisitioning
  • B. Invoice processing
  • C. Source assignment
  • D. Supplier evaluation

Answer: D

 

NEW QUESTION 21
What function compares assigned funds to the budget of a work breakdown structures (WBS) element?
Response:

  • A. Results analysis
  • B. Cost forecast
  • C. Availability control
  • D. Settlement

Answer: D

 

NEW QUESTION 22
What are the process steps in corrective maintenance?
Response:

  • A. Create Task List
    Create Plan
    Schedule Plan
    Release Order
    Complete Order
  • B. Create Notification
    Release Order
    Execute Order
    Complete Order
    Billing
  • C. Create Task List
    Create Plan
    Schedule Plan
    Complete Order
    Billing
  • D. Create Notification
    Create Order
    Release Order
    Execute Order
    Complete Order

Answer: D

 

NEW QUESTION 23
Where do you maintain primary and secondary cost elements?
Response:

  • A. Cost Element Accounting
  • B. General Ledger Accounting
  • C. Cost Center Accounting
  • D. Profit Center Accounting

Answer: B

 

NEW QUESTION 24
You have created an asset master data record. Which other master data record can be created synchronously?
Response:

  • A. Primary cost element
  • B. Cost center
  • C. Functional location
  • D. Equipment

Answer: D

 

NEW QUESTION 25
Which SAP Fiori application types use the SAP HANA data layer directly?
There are TWO correct answers for this Question
Response:

  • A. Analytical
  • B. Fact sheet
  • C. Web Dynpro
  • D. Transactional

Answer: A,B

 

NEW QUESTION 26
What MRP control parameter defines the scope of a planning run?
Response:

  • A. Processing key
  • B. Lot size
  • C. Procurement type
  • D. Planning mode

Answer: A

 

NEW QUESTION 27
What does the material ledger in SAP S/4HANA enable?
There are TWO correct answers for this Question
Response:

  • A. Recording of all business transactions
  • B. Reporting for parallel accounting
  • C. Reporting of all materials required during maintenance processing
  • D. Material valuation in multiple currencies

Answer: B,D

 

NEW QUESTION 28
Which objects can you settle?
There are TWO correct answers for this Question
Response:

  • A. Maintenance order
  • B. Cost center
  • C. Work breakdown structure (WBS) element
  • D. Profitability segment

Answer: A,B

 

NEW QUESTION 29
In which situation would you create an equipment master record?
There are TWO correct answers for this Question
Response:

  • A. To report the usage time of an object at a functional location
  • B. To report and track preventive maintenance tasks for an object
  • C. To functionality represent the technical system structures in your company
  • D. To report the effects of usage on the likelihood of damage to the installed equipment

Answer: A,B

 

NEW QUESTION 30
Which of the following master records are directly assigned to a company code?
There are TWO correct answers for this Question
Response:

  • A. Fixed asset
  • B. Cost center
  • C. Material master
  • D. Activity type

Answer: A,B

 

NEW QUESTION 31
What are the benefits of using a business partner in SAP S/4HANA?
There are TWO correct answers for this Question
Response:

  • A. You can maintain multiple addresses for an entity
  • B. It provides a harmonized architecture
  • C. General data is unique to each role
  • D. Vendors are managed separately from customers

Answer: A,B

 

NEW QUESTION 32
An internal activity price can be assigned to the combination of activity type and which project?
Response:

  • A. Work center
  • B. Funds center
  • C. Cost center
  • D. Profit center

Answer: C

 

NEW QUESTION 33
What master data records are used in advanced planning?
There are THREE correct answers for this Question
Response:

  • A. Work center
  • B. Product
  • C. Resource
  • D. Location
  • E. Bill of material

Answer: B,C,D

 

NEW QUESTION 34
What fields are required when you create a cost center?
There are TWO correct answers for this Question
Response:

  • A. Address
  • B. Hierarchy area
  • C. Person responsible
  • D. Department

Answer: B,C

 

NEW QUESTION 35
What does Management Accounting provide?
There are 2 correct answers to this question
Response:

  • A. Reports that meet accounting standards and principles
  • B. Profitability analysis of market segments
  • C. Account balances for customers and vendors
  • D. Information used for internal areas of responsibility

Answer: B,D

 

NEW QUESTION 36
At which points in the order-to-cash process are postings made to the general ledger?
There are TWO correct answers for this Question
Response:

  • A. Saving the invoice
  • B. Saving the sales order
  • C. Posting a goods issue
  • D. Confirming a transfer order

Answer: A,C

 

NEW QUESTION 37
Which enterprise structure elements are in a sales area?
There are TWO correct answers for this Question
Response:

  • A. Company code
  • B. Plant
  • C. Division
  • D. Distribution channel

Answer: C,D

 

NEW QUESTION 38
What tasks are performed for legal reporting?
There are TWO correct answers for this Question
Response:

  • A. Calculate production variances
  • B. Perform inventory valuation
  • C. Track company car costs
  • D. Create a balance sheet

Answer: B,D

 

NEW QUESTION 39
......

Exam Engine for C-TS410-1809 Exam Free Demo & 365 Day Updates: https://www.lead2passed.com/SAP/C-TS410-1809-practice-exam-dumps.html