NEW QUESTION 17
Which is a typical characteristic of 'business as usual' work?

  • A. It is delivered by an established team
  • B. It requires a specific dedicated project manager
  • C. It is delivered by a temporary team
  • D. It is executed by program management

Answer: A

 

NEW QUESTION 18
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?

  • A. Effective
  • B. Typical
  • C. Preferable

Answer: A

 

NEW QUESTION 19
Which is a benefit of the Lean Startup approach to releasing a product?

  • A. It enables the release plans to be synchronized with the PRINCE2 plans
  • B. It reduces the number of people needed to manage a release of a product
  • C. It provide a technique to reduce the testing of a product before release
  • D. It provides quick feedback that can be responded to at the earliest opportunity

Answer: A

 

NEW QUESTION 20
Which statement explains the PRINCE2 Agile behavior of 'exploration'?

  • A. It empowers the project management team at the delivery level
  • B. It uses the most effective channel to communicate information
  • C. It seeks out feedback collaboratively from project stakeholders
  • D. It displays the progress rate to everyone using burn-down charts

Answer: C

 

NEW QUESTION 21
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Sprint review
  • B. Sprint planning
  • C. Daily scrum
  • D. Increment

Answer: C

 

NEW QUESTION 22
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By flexing what is produced to stay in control and deliver value
  • B. By using the Agilometer to assess the project environment
  • C. By emphasizing tolerances on what is being delivered
  • D. By fitting releases into planned management stages

Answer: A

 

NEW QUESTION 23
Which statement about the 'embrace change' target is CORRECT?

  • A. It reduces testing in order to meet deadlines
  • B. It reduces the planning of dependencies between projects
  • C. It minimizes the time needed to train a new team member
  • D. It encourages the customer to raise new ideas

Answer: D

 

NEW QUESTION 24
To help with prioritization, what is MOST important when understanding the difference between scope and quality?

  • A. Defining non-functional requirements before functional requirements
  • B. Combining functional and non-functional requirements
  • C. Creating non-functional requirements with user stories
  • D. Differentiating functional from non-functional requirements

Answer: D

 

NEW QUESTION 25
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance can be fixed and flexed
  • B. Cost tolerance can be fixed or flexed
  • C. Cost tolerance is flexed
  • D. Cost tolerance is fixed

Answer: C

 

NEW QUESTION 26
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 1 and 2
  • B. 3 and 4
  • C. 2 and 3
  • D. 1 and 4

Answer: D

 

NEW QUESTION 27
What is the definition of a timebox?

  • A. A period where work is carried out to achieve a goal
  • B. A description of the rate of progress a team is making
  • C. A regular event that looks at how processes can be improved
  • D. A tool to write a requirement in the form of who, what and why

Answer: A

 

NEW QUESTION 28
How does agile address the risk associated with the project not being fully understood at the beginning?

  • A. By avoiding too much detail at the start
  • B. By requiring details at the start
  • C. By preventing the analysis of details at the start
  • D. By allowing a lot of detail at the start

Answer: C

 

NEW QUESTION 29
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by using the same team members
  • B. It delivers the early realization of benefits
  • C. It is achieved by allowing enough time for testing
  • D. It gives confidence on the progress of the project

Answer: B

Explanation:
Reference:
%20level%20is%20met

 

NEW QUESTION 30
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.

  • A. 1 and 2
  • B. 1 and 4
  • C. 3 and 4
  • D. 2 and 3

Answer: C

 

NEW QUESTION 31
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. T-shirt sizing
  • B. Trading
  • C. Rationalism
  • D. Visioning

Answer: C

 

NEW QUESTION 32
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It applies primarily to the long term, such as a project or a program
  • B. It is the primary reason why the tolerance for cost is set to zero
  • C. It prevents compromising the overall quality level of the product
  • D. It results in the early delivery of a minimum viable product

Answer: B

 

NEW QUESTION 33
How should product-based planning be used as part of PRINCE2 Agile?

  • A. To plan by focusing on the features required
  • B. To enable team planning to be predictive
  • C. To track progress against the team plan
  • D. To create the project plan using empiricism

Answer: A

 

NEW QUESTION 34
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should make decisions based on the Agilometer risks
  • B. The project board should attend regular project progress meetings
  • C. The project board should increase the stage-level time tolerance
  • D. A project board member should fulfill the product owner role within a delivery team

Answer: D

 

NEW QUESTION 35
Which process can take place during a release review workshop?

  • A. Directing a project
  • B. Managing product delivery
  • C. Managing a stage boundary
  • D. Controlling a stage

Answer: B

 

NEW QUESTION 36
Which statement describes the Kanban approach?

  • A. It is an iterative timeboxed approach that helps teams generate value
  • B. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
  • C. It was originally focused in creating new companies and is now used to speed up product delivery
  • D. It is used to make system improvements using visualization and by controlling work in progress

Answer: D

 