PRINCE2 PRINCE2-Agile-Foundation (PRINCE2 Agile Foundation) Exam is a certification exam that is designed to test the knowledge and understanding of individuals in the field of project management. PRINCE2-Agile-Foundation exam is specifically aimed at individuals who are interested in learning about the PRINCE2 Agile methodology, which is a combination of two popular project management frameworks – PRINCE2 and Agile.
NEW QUESTION # 52
Which statement defines a PRINCE2 principle?
- A. A PRINCE2 project defines its quality management approach
- B. A PRINCE2 project is tailored to suit the competitor's environment
- C. A PRINCE2 project ensures a consistent approach to risk management
- D. A PRINCE2 project is monitored and controlled on a stage-by-stage basis
Answer: D
NEW QUESTION # 53
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To use empiricism, based on knowledge that comes from experience
- B. To fail fast, if you are going to fail
- C. To build, measure, learn from your experiences
- D. To create a minimum viable product to manage uncertainty
Answer: A
Explanation:
Reference: https://publications.axelos.com/PRINCE2Agile2016/content.aspx?
page=pra_127&showNav=true&expandNav=true
NEW QUESTION # 54
What should be emphasized when tailoring the PRINCE2 Progress theme?
- A. Monitoring what is being delivered
- B. Planning resources
- C. Tracking time and cost
- D. Assessing the impact of risks
Answer: A
NEW QUESTION # 55
Which organizational level is responsible for day-to-day management and decision making within the constraints established by the project manager?
- A. Directing
- B. Delivering
- C. Managing
- D. Commissioning
Answer: B
Explanation:
The Delivering level is responsible for the day-to-day management and decision-making within the constraints set by the project manager. Delivering teams carry out the actual work to create the project products and manage their activities under the project's governance framework. The Project Manager manages the overall project, while directing sets the strategic direction and commissioning authorizes initiation.
This separation ensures clear responsibilities and empowers the delivery teams to self-manage within defined boundaries.
Reference: PRINCE2 Agile Foundation Version 2, Section 3.4 "Project Management Structure," and PRINCE2 Agile Study Guide, Chapter 3.
NEW QUESTION # 56
Why are team working agreement produced?
- A. To create structure so that the team manager can assess individual performance
- B. To ensure that the delivery team members comply with company policy
- C. To make the team rules visible to the project manager for monitoring purposes
- D. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
Answer: D
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION # 57
What should be decided when configuring PRINCE2 effectively?
- A. What to remove and where to add guidance
- B. Where to put the emphasis and where to add guidance
- C. What to significantly change to create the right blend
- D. Which areas are not enabled to work with agile
Answer: C
NEW QUESTION # 58
What is a role of personas in the 'business case' practice?
- A. To group users based on demographic data
- B. To ensure project timelines are met
- C. To differentiate between product versions
- D. To identify and articulate specific user benefits
Answer: D
Explanation:
Personas in PRINCE2 Agile serve as fictional, archetypal users representing the needs, behaviors, and goals of real users. In the business case practice, personas are used to identify and articulate specific user benefits.
This ensures the project focuses on delivering value that meets the actual needs of different user groups.
By understanding personas, teams can tailor product features and prioritize requirements that provide meaningful benefits, thereby strengthening the business case and increasing stakeholder buy-in. Personas help clarify who will use the product, what problems they face, and how the solution delivers value.
Personas go beyond demographic grouping (A); they are detailed profiles including motivations and pain points. They do not relate directly to timelines (B) or product version differentiation (D).
Using personas aligns with agile principles of customer focus and continuous stakeholder engagement embedded in PRINCE2 Agile.
Reference: PRINCE2 Agile Foundation Version 2, Section 7.1 "Using Personas in Business Case," and PRINCE2 Agile Study Guide, Chapter 7.
NEW QUESTION # 59
When creating the project product description, how should the purpose of the project product be defined?
- A. As an opportunity
- B. As an outcome
- C. As a vision
- D. As a goal
Answer: B
NEW QUESTION # 60
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 1 and 2
- B. 3 and 4
- C. 1 and 4
- D. 2 and 3
Answer: C
NEW QUESTION # 61
Which of the following is a prioritized list of the requirements for a product?
- A. Release map
- B. Backlog
- C. Project log
- D. Project canvas
Answer: B
Explanation:
In PRINCE2 Agile, a Backlog is the prioritized list of requirements, features, or user stories that define what needs to be delivered for a product. It is a dynamic and evolving list that is continually refined and re- prioritized to ensure the most valuable work is done first. The backlog acts as a single source of truth for what the team needs to deliver and provides transparency to stakeholders regarding progress and priorities. It aligns with agile principles and practices such as Scrum, where the Product Backlog contains all desired work for the product.
The Project Canvas is a high-level tool used for defining project scope and objectives, the Release Map plans releases and iterations, and the Project Log tracks issues, risks, and actions but does not list prioritized requirements.
Reference: PRINCE2 Agile Foundation Version 2, Section 5.3 "Agile Concepts," and PRINCE2 Agile Study Guide, Chapter 5, "Products and Backlogs."
NEW QUESTION # 62
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?
- A. How to select which Agile framework should be favoured
- B. How to adapt the PRINCE2 management products
- C. How to decide whether PRINCE2 is appropriate
- D. How to calculate the project budget and cost tolerance
Answer: B
NEW QUESTION # 63
Which BEST describes the senior user role when tailoring the organization theme?
- A. A 'coach'
- B. A 'super product owner'
- C. An 'executive sponsor'
- D. An 'agile sponsor'
Answer: B
Explanation:
Reference: https://publications.axelos.com/PRINCE2Agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_52
NEW QUESTION # 64
Which workshop focuses on team growth and improvements in working practices?
- A. Project kickoff workshop
- B. Progress review workshop
- C. Team retrospective workshop
- D. Team planning workshop
Answer: C
Explanation:
The Team Retrospective Workshop is explicitly designed to facilitate team growth and continuous improvement in working practices. It is a fundamental agile practice where the team reflects on the recently completed work or sprint to identify what went well, what didn't, and what could be improved. The goal is to foster an environment of trust and openness, enabling teams to discuss challenges and successes honestly.
Retrospectives promote inspect and adapt principles by encouraging teams to continuously evaluate their processes, collaboration, and tools. They help uncover systemic issues, process bottlenecks, or interpersonal challenges that may be impeding productivity or quality. Teams use this feedback to implement actionable improvements, which can range from adjusting communication methods to refining definitions of done or ready.
This workshop supports a key agile mindset-continuous learning and improvement-which directly contributes to team maturity, performance, and morale. Importantly, retrospectives are not about assigning blame but rather about fostering a growth mindset that accepts change as an opportunity to evolve.
While Project Kickoff Workshops (A) initiate project alignment and Progress Review Workshops (C) monitor project status, they do not primarily focus on team process improvements. The Team Planning Workshop (D) is concerned with planning upcoming work, not retrospection.
In PRINCE2 Agile, retrospectives are a critical tool to blend traditional project management with agile principles by promoting regular reflection and incremental enhancements.
Reference: PRINCE2 Agile Foundation Version 2, Section 6.5 "Retrospectives and Continuous Improvement," and PRINCE2 Agile Study Guide, Chapter 6.
NEW QUESTION # 65
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?
- A. Because it explains how a small company can grow using traditional technologies
- B. Because it is designed to manage projects, delivering products in timeboxes
- C. Because running a project and setting up a new business are the same
- D. Because it enables agile to be used in challenging and uncertain situations
Answer: D
Explanation:
Reference: https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_127&showNav=true&expandNav=true
NEW QUESTION # 66
Which statement BEST describes the PRINCE2 Agile guidance for change?
- A. The delivery team should quickly approve changes to the project baseline
- B. The delivery team should be authorized to make changes at the detailed level
- C. The executive should approve delivery level changes to harness the benefits of positive change
- D. The executive should manage changes dynamically at the detailed level
Answer: B
NEW QUESTION # 67
What is an epic?
- A. A detailed feature
- B. A low-level requirement
- C. A high-level requirement
- D. A fine-grained user story
Answer: C
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?
page=pra_160&showNav=true&expandNav=true
NEW QUESTION # 68
Which statement about velocity is CORRECT?
- A. It is shown by the ideal line on a bum-down chart
- B. It is based on the concept of rationalism
- C. It describes how much work is getting done
- D. It tracks the time and cost of a timebox
Answer: C
Explanation:
Reference: https://worldofagile.com/blog/velocity/
NEW QUESTION # 69
Which of the following uses a flow-based approach to control work in progress?
- A. Scrum
- B. Agilometer
- C. Kanban
- D. Lean
Answer: C
Explanation:
Kanban uses a flow-based approach to visualize and control work in progress (WIP). It emphasizes limiting WIP to improve flow and reduce bottlenecks, with continuous monitoring via Kanban boards. This approach supports flexibility, transparency, and efficiency in managing tasks.
The Agilometer (A) measures agility, Lean (B) is a broad philosophy focusing on waste reduction, and Scrum (D) is an iterative framework but uses time-boxed sprints rather than flow-based control.
Reference: PRINCE2 Agile Foundation Version 2, Section 5.5 "Agile Techniques," and PRINCE2 Agile Study Guide, Chapter 5.
NEW QUESTION # 70
What role does AI play in addressing project complexity within PRINCE2 Agile?
- A. It helps reduce uncertainty and ambiguity associated with change initiatives
- B. It adds layers of complexity through excessive automation
- C. It ensures stakeholder involvement in all decision-making
- D. It helps reduce all sources of project complexity
Answer: A
Explanation:
Artificial Intelligence (AI) in PRINCE2 Agile is recognized as a tool that can assist in reducing uncertainty and ambiguity by providing data-driven insights, predictive analytics, and automation of routine tasks. This support helps teams better understand changing environments and respond faster, thereby addressing complexity associated with change initiatives.
While AI can add complexity if misused, PRINCE2 Agile focuses on its beneficial role in supporting decision- making and reducing unknowns rather than complicating governance or communication.
Reference: PRINCE2 Agile Foundation Version 2, Section 8.5 "Technology and Agile," and PRINCE2 Agile Study Guide, Chapter 8.
NEW QUESTION # 71
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By using the Agilometer to assess the project environment
- B. By emphasizing tolerances on what is being delivered
- C. By flexing what is produced to stay in control and deliver value
- D. By fitting releases into planned management stages
Answer: C
NEW QUESTION # 72
What is an epic?
- A. The set of products handed over to the users
- B. A high-level user story that is quite broad or vague
- C. A detailed user story with high business value
- D. A prioritized list of requirements to be delivered in a sprint
Answer: B
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?
page=pra_160&showNav=true&expandNav=true
NEW QUESTION # 73
Which is a benefit of the Lean Startup approach to releasing a product?
- A. It provide a technique to reduce the testing of a product before release
- B. It provides quick feedback that can be responded to at the earliest opportunity
- C. It enables the release plans to be synchronized with the PRINCE2 plans
- D. It reduces the number of people needed to manage a release of a product
Answer: C
Explanation:
Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_170&showNav=true&expandNav=true
NEW QUESTION # 74
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It is achieved by using the same team members
- B. It is achieved by allowing enough time for testing
- C. It gives confidence on the progress of the project
- D. It delivers the early realization of benefits
Answer: D
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION # 75
What describes essential aspects of project management that must be applied consistently and throughout the project lifecycle?
- A. The people element
- B. The project context
- C. The PRINCE2 practices
- D. The PRINCE2 processes
Answer: C
Explanation:
The PRINCE2 practices represent the essential aspects of project management that must be applied consistently from start to finish in every project. These practices cover key areas such as managing risks, issues, quality, plans, progress, and change. They provide structured guidance and tools to ensure the project remains viable, controlled, and aligned with business objectives.
While processes define the stages and flow of activities, and the people element refers to roles and skills, practices are the ongoing activities and controls embedded throughout the project lifecycle. The project context shapes how practices and processes are tailored but does not itself define the consistent elements.
This consistent application of practices supports governance, transparency, and control, critical for successful project outcomes.
Reference: PRINCE2 Agile Foundation Version 2, Section 3.2 "The PRINCE2 Practices," and PRINCE2 Agile Study Guide, Chapter 3.
NEW QUESTION # 76
......