Free SAP C_TS412_1909 Exam Questions & Answer from Training Expert Lead2Passed [Q34-Q55]

Share

Free SAP C_TS412_1909 Exam Questions & Answer from Training Expert Lead2Passed

Top SAP C_TS412_1909 Courses Online


SAP C_TS412_1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Project Structures > 12%

Name the components of Work Breakdown Structure, Network and activities, Milestones

Resources > 12%

Describe how the Resource Planning process integrates with HCM

Cost and Budgets > 12%

Describe procedures for establishing budgets and reporting costs.

Revenues and Payments > 12%

Describe the characteristics of Revenues & Payments.

Dates > 12%

Describe the importance of various dates which can be tracked for projects

Material > 12%

Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement

Reporting < 8%

Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports



SAP C_TS412_1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

 

NEW QUESTION 34
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.

  • A. Generate purchase requisition
  • B. Stock transfer posting
  • C. Generate delivery
  • D. Confirm production order
  • E. Cancel goods issue

Answer: A,B,C

 

NEW QUESTION 35
What functionality can you perform with activity elements?

  • A. Assign work centers and capacities
  • B. Create relationships
  • C. Assign material
  • D. Schedule WBS elements

Answer: B

 

NEW QUESTION 36
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Sales order items
  • B. Project definition
  • C. WBS elements
  • D. Milestones

Answer: A,C

 

NEW QUESTION 37
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.

  • A. Work
  • B. Activity type
  • C. Profit center
  • D. Duration

Answer: A,B

 

NEW QUESTION 38
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Network header
  • B. Activity element
  • C. Activity
  • D. Milestone

Answer: C

 

NEW QUESTION 39
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

  • A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
  • B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
  • C. You can only maintain the actual start of a WBS element if the finish date is not maintained.
  • D. You can always maintain the actual start and finish date of a WBS element.

Answer: A,B

 

NEW QUESTION 40
How are earliest dates and latest dates of activities scheduled?

  • A. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
  • B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
  • C. Earliest dates and latest dates are scheduled by forward scheduling.
  • D. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.

Answer: B

 

NEW QUESTION 41
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.

  • A. The procurement type of the material must be internal.
  • B. An MRP group must be assigned.
  • C. The exact lot size procedure must be used.
  • D. The materials must allow sales order or project stock.

Answer: B,D

 

NEW QUESTION 42
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Valuation in different currencies
  • B. Usage of different line IDs
  • C. Billing WBS elements belonging to different company codes
  • D. Assignments of different accounts for postings to financial accounting

Answer: D

 

NEW QUESTION 43
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Project simulations can create purchase requisitions.
  • B. Multiple project simulations can be used simultaneously.
  • C. Project simulations allow posting of actual data.
  • D. Project simulations can be used to plan structures and costs.
  • E. Project simulations can be created without using an operational project as a template.

Answer: B,D,E

 

NEW QUESTION 44
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.

  • A. The availability check for material components indicates missing parts.
  • B. The material is assigned to the activity as a non-stock material.
  • C. The material master is set to external procurement.
  • D. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".

Answer: A,D

 

NEW QUESTION 45
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Individual overview capacity requirements
  • B. Structure overview
  • C. None
  • D. Capacity load work center view
  • E. Extended capacity evaluation

Answer: A

 

NEW QUESTION 46
Which planning method can prevent further rescheduling of activities?

  • A. Capacity requirements activation
  • B. Workforce planning
  • C. Capacity leveling
  • D. Partial confirmation of activities

Answer: A

 

NEW QUESTION 47
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

  • A. Trigger automatic capacity leveling inside the project planning board.
  • B. Maintain subordinate internal activity elements assigned to other work centers.
  • C. Increase the capacities of the work center in the project planning board.
  • D. Shift activities backward or forward on the time axis where more capacities are available.

Answer: A,D

 

NEW QUESTION 48
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Network profile
  • B. Project profile
  • C. Data entry profile
  • D. Network type

Answer: C

 

NEW QUESTION 49
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. A workflow can be triggered to inform the purchasing group.
  • B. The system automatically creates a new purchase requisition with the difference to the original quantity.
  • C. The purchase order is updated automatically to match the new quantity while saving the project.
  • D. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).

Answer: A

 

NEW QUESTION 50
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Results analysis key
  • B. Investment profile
  • C. Costing sheet
  • D. Settlement rule

Answer: C

 

NEW QUESTION 51
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.

  • A. By default, critical activities have a float time, which is less than or equal to zero.
  • B. The maximum size of a free float is as large as the total float of an activity.
  • C. Activities with the time constraint "Must start on" always have a negative float time.
  • D. The float time of WBS elements is calculated by extrapolation.
  • E. Float time can be negative.

Answer: A,C,E

 

NEW QUESTION 52
How can you confirm the working hours of different work centers for a single activity?

  • A. Enter direct activity allocation assigning multiple work centers.
  • B. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.
  • C. Assign multiple work centers to the activity.
  • D. Enter multiple work centers within a single confirmation.

Answer: A

 

NEW QUESTION 53
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?

  • A. Missing material availability
  • B. Missing authorizations to release material components
  • C. Missing budget for material components
  • D. Missing reservations for material components

Answer: B

 

NEW QUESTION 54
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.

  • A. In the project version
  • B. In the operative WBS element
  • C. In the project profile
  • D. In the project definition of a standard WBS
  • E. In the project type

Answer: B,C,D

 