NEW QUESTION 11
What functionality can you perform with activity elements?

  • A. Schedule WBS elements
  • B. Assign work centers and capacities
  • C. Assign material
  • D. Create relationships

Answer: D

 

NEW QUESTION 12
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.

  • A. Preliminary purchase requisition for WBS element
  • B. Purchase requisition and Reservation for WBS element
  • C. Planned order
  • D. Third-party order
  • E. Reservation for WBS element

Answer: A,B,E

 

NEW QUESTION 13
To which object can you assign a factory calendar?

  • A. Milestone
  • B. Relationship
  • C. Network header
  • D. Material component

Answer: C

 

NEW QUESTION 14
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

  • A. Saving a goods receipt
  • B. Saving a supplier invoice
  • C. Saving a service entry sheet
  • D. Saving a purchase order

Answer: A,C

 

NEW QUESTION 15
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

  • A. The network is assigned to a sales order item.
  • B. The network activity is assigned to a WBS element.
  • C. The Project Stock indicator is set in the project definition (non-valuated or valuated).
  • D. The material master of the component must permit project stock management.
  • E. A procurement indicator must be assigned to the activity.

Answer: C,D,E

 

NEW QUESTION 16
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.

  • A. Material master
  • B. WBS element
  • C. BOM item
  • D. Network activity

Answer: C,D

 

NEW QUESTION 17
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Progress analysis
  • B. Results analysis
  • C. Settlement
  • D. Milestone trend analysis
  • E. Confirmations

Answer: A,B,C

 

NEW QUESTION 18
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. A subnetwork cannot be defined for a superior subnetwork.
  • B. Subnetworks must be scheduled separately from the superior network.
  • C. The scheduling type of a subnetwork is always copied from the superior network.
  • D. Maintenance orders can be defined as subnetworks.

Answer: D

 

NEW QUESTION 19
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

  • A. Actual dates of the network activity
  • B. Basic dates of the network activity
  • C. Forecast dates of the WBS
  • D. Basic dates of the WBS

Answer: B

 

NEW QUESTION 20
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.

  • A. Relationships can be used to connect activities of different networks.
  • B. Material components can be assigned to activity elements.
  • C. A network can be activity-account-assigned and header-account-assigned.
  • D. A network activity can be assigned to several WBS elements.

Answer: A,C

 

NEW QUESTION 21
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

  • A. A delivery document type must be configured.
  • B. A sold to party is necessary.
  • C. A sales order must be created in advance.
  • D. A shipping point is necessary.

Answer: B,D

 

NEW QUESTION 22
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

  • A. The person responsible for the work center
  • B. The person responsible for the superior WBS element
  • C. The MRP controller for the network
  • D. The person responsible for the network activity

Answer: C

 

NEW QUESTION 23
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.

  • A. Goods receipt of a non-stock item
  • B. Goods receipt into unvaluated project stock
  • C. Goods receipt into valuated project stock
  • D. Recording of external services in the service entry sheet

Answer: B,D

 

NEW QUESTION 24
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.

  • A. Project simulations allow posting of actual data.
  • B. Project simulations can create purchase requisitions.
  • C. Multiple project simulations can be used simultaneously.
  • D. Project simulations can be created without using an operational project as a template.
  • E. Project simulations can be used to plan structures and costs.

Answer: C,D,E

 

NEW QUESTION 25
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Network profile
  • B. Data entry profile
  • C. Network type
  • D. Project profile

Answer: B

 

NEW QUESTION 26
......