NEW QUESTION 11
What functionality can you perform with activity elements?
- A. Schedule WBS elements
- B. Assign work centers and capacities
- C. Assign material
- D. Create relationships
Answer: D
NEW QUESTION 12
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Preliminary purchase requisition for WBS element
- B. Purchase requisition and Reservation for WBS element
- C. Planned order
- D. Third-party order
- E. Reservation for WBS element
Answer: A,B,E
NEW QUESTION 13
To which object can you assign a factory calendar?
- A. Milestone
- B. Relationship
- C. Network header
- D. Material component
Answer: C
NEW QUESTION 14
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a goods receipt
- B. Saving a supplier invoice
- C. Saving a service entry sheet
- D. Saving a purchase order
Answer: A,C
NEW QUESTION 15
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The network is assigned to a sales order item.
- B. The network activity is assigned to a WBS element.
- C. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- D. The material master of the component must permit project stock management.
- E. A procurement indicator must be assigned to the activity.
Answer: C,D,E
NEW QUESTION 16
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Material master
- B. WBS element
- C. BOM item
- D. Network activity
Answer: C,D
NEW QUESTION 17
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Progress analysis
- B. Results analysis
- C. Settlement
- D. Milestone trend analysis
- E. Confirmations
Answer: A,B,C
NEW QUESTION 18
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. A subnetwork cannot be defined for a superior subnetwork.
- B. Subnetworks must be scheduled separately from the superior network.
- C. The scheduling type of a subnetwork is always copied from the superior network.
- D. Maintenance orders can be defined as subnetworks.
Answer: D
NEW QUESTION 19
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
- A. Actual dates of the network activity
- B. Basic dates of the network activity
- C. Forecast dates of the WBS
- D. Basic dates of the WBS
Answer: B
NEW QUESTION 20
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. Relationships can be used to connect activities of different networks.
- B. Material components can be assigned to activity elements.
- C. A network can be activity-account-assigned and header-account-assigned.
- D. A network activity can be assigned to several WBS elements.
Answer: A,C
NEW QUESTION 21
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A delivery document type must be configured.
- B. A sold to party is necessary.
- C. A sales order must be created in advance.
- D. A shipping point is necessary.
Answer: B,D
NEW QUESTION 22
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The person responsible for the work center
- B. The person responsible for the superior WBS element
- C. The MRP controller for the network
- D. The person responsible for the network activity
Answer: C
NEW QUESTION 23
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt of a non-stock item
- B. Goods receipt into unvaluated project stock
- C. Goods receipt into valuated project stock
- D. Recording of external services in the service entry sheet
Answer: B,D
NEW QUESTION 24
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Project simulations allow posting of actual data.
- B. Project simulations can create purchase requisitions.
- C. Multiple project simulations can be used simultaneously.
- D. Project simulations can be created without using an operational project as a template.
- E. Project simulations can be used to plan structures and costs.
Answer: C,D,E
NEW QUESTION 25
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Network profile
- B. Data entry profile
- C. Network type
- D. Project profile
Answer: B
NEW QUESTION 26
......