Best Quality Microsoft MB-320 Exam Questions Lead2Passed Realistic Practice Exams [2021]
Critical Information To Microsoft Dynamics 365 Supply Chain Management, Manufacturing Pass the First Time
Target Candidate
Those who MB-320 test is intended for are functional consultants. Thus, the individuals’ background should include possessing awareness regarding concepts that touch on principles of accounting as well as financial operations and are aimed at businesses, field service, customer service, retail, manufacturing, as well as the management of the supply chain. Ideally, the possible candidates specialize in at least one feature related to Finance as well as Operations, and that includes finance, supply chain management, and manufacturing.
NEW QUESTION 11
A company uses separate finished good item numbers for size variations of the same product.
The company wants to minimize the number of variously-sized items that are created.
You need to perform the setup to allow variants in size to the product master.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
Explanation
Reference:
https://gfeaxblog.wordpress.com/2017/09/28/o365-how-to-create-product-masters/
NEW QUESTION 12
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You have created the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You create separate subcontracting purchase orders to account for the service. You attempt to add the service item to the BOM. The system generates an error.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
1 - Create a new item model group and clear the stocked product option.
2 - Assign the item model group and select the stocked product option.
3 - Add the service item to the BOM.
NEW QUESTION 13
A company implements Dynamics 365 for Finance and Operations.
Production orders are generated for products directly from projects. You create the following production order:
Use the drop-down menus to select the answer choice that answers each question based on the information presented in the graphic. NOTE: Each correct selection is worth one point.
Answer:
Explanation:
Explanation
NEW QUESTION 14
A skateboard manufacturer uses route operations to schedule resources and estimate units per hour. All products use the sample sub assembly item and resource sanding process.
You observe an increase in the number of units a sanding belt resource can produce. The production schedule is now inaccurate due to the number of units the sanding belt line can produce.
You must make a permanent change to the number of units the resource can produce for all future orders.
You need to adjust the process quantity on the route operation.
Which three actions should you perform in sequence? To answer, move the appropriate actions form the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
Explanation
NEW QUESTION 15
You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods.
The company must track variances in material compared to the original estimated amount. You must only use one picking list journal for each production order.
You need to post a picking list that accounts for the material required to produce 105 finished goods.
What should you do?
- A. Report as finished five additional units into the good quantity and post a picking list for only the originally estimated amount.
- B. When creating the lines for a picking list, select the estimated consumption option and override the consumption field with the actual amount to be consumed.
- C. Post a picking list for 100 to account for the originally estimated amount. Post an additional picking list to account for the equivalent amount of material to produce 5 finished goods.
- D. In the Bill of materials production details, edit the estimated amount for each line to equal 105 units of raw material.
Answer: B
NEW QUESTION 16
You need to modify the production order defaults for the manufacturing execution production order Start process.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
Answer:
Explanation:
Explanation
NEW QUESTION 17
A company produces various products using Process manufacturing.
The manufacturer makes two co-products from a formula and rarely produces the primary formula item.
The costs of making the co-products are inflated. The manufacturer must update the costs of producing the co-products and change the formula to not produce the primary formula item.
You need to change the primary formula item type.
What should you do?
- A. Change the cost of the primary formula item to zero and then recalculate the item cost
- B. Change the primary formula item to use the planning item type
- C. Associate the costs to produce by-products with the items
- D. Change the production type to Bill of materials and recalculate the item cost
Answer: B
NEW QUESTION 18
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
1.) Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01
2.) Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell
3.) Create a production flow process activity using the painting work cell and the service item as the picking activity
4.) Create a service term on the activity to tie the purchase agreement to the activity Does this solution meet the goal?
- A. Yes
- B. No
Answer: A
Explanation:
Section: Create and manage production and lean orders
Explanation/Reference:
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity- based-subcontracting
NEW QUESTION 19
A company produces generic and name-brand paper plates in the same factory using standard costing and using the same Bill of materials and routes to produce both products. The finance and production teams want a way to view individual raw material consumption costs in the ledger. You need to add a production group to the finished good to control postings to the ledger. What should you do?
- A. Update the cost of the generic finished good item.
- B. Create a production group for the finished good item.
- C. Create a production pool for the finished good item.
- D. Create a new Bill of materials with alternate costs for the raw material.
Answer: B
NEW QUESTION 20
A company uses Dynamics 365 for Finance and Operations for Process manufacturing.
Employees spend considerable time cleaning and setting up machines in a specific area between production orders. You must group production activities to optimize cleaning and set up time.
You need to set up the system.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: More than one order of answer choices is correct. You will receive credit for any of the correct orders you select.
Answer:
Explanation:
NEW QUESTION 21
A manufacturer uses route operations and job scheduling.
You use a unique calendar for a conveyor line. The company observes a decrease in the number of hours a conveyor line resource is operational due to breakdowns. You must make a temporary change to the number of hours the resource is available.
You need to adjust the efficiency percentage for the conveyor line calendar.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:

NEW QUESTION 22
A customer produces light projection toys for holiday decorations throughout the year. The production process creates the projections toy at the following work cells stands, main assembly, electric, visuals, and packaging.
Vendors must create visual templates for the company for each season. They must manage the transfer of visual templates to the warehouse. Each transfer for each vendor must use the same purchase agreement.
You need to configure the subcontracted transfer activity.
What should you do?
- A. Set the transfer activity Freighted by value to . Ensure that purchase agreements include the vendor ID of the warehouse.
- B. Set the transfer activity Freighted by value to . Ensure that purchase agreements include the vendor ID of the vendor.
- C. Set the transfer activity Freighted by value to . Ensure that purchase agreements include the vendor ID of the warehouse.
- D. Set the transfer activity Freighted by value to . Ensure that purchase agreements include the vendor ID of the warehouse.
- E. Set the transfer Freighted by value to Shipper. Ensure that purchase agreements include the vendor ID of the vendor.
- F. Set the transfer Freighted by value to Carrier. Ensure that purchase agreements include the vendor ID of the vendor.
Answer: A
Explanation:
Explanation
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity-based
NEW QUESTION 23
A company is looking to use Dynamics 365 Supply Chain Management.
The company is in the process of redesigning and retooling an existing manufacturing plant to group similar, cellular operations to improve efficiency and minimize wasted time between operations. They want to locate raw materials close to where they are needed without losing reorder visibility.
You need to set up their environment.
Which kind of production type should you implement?
- A. Manufacturing execution
- B. Process manufacturing
- C. Lean manufacturing
- D. Discrete manufacturing
Answer: C
NEW QUESTION 24
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company implements Dynamics 365 for Finance and Operations for their Lean manufacturing environment.
There has been an engineering change to a fixed quantity product that is in production. This change will add an additional processing step as the second step. The existing version must be phased out and replaced by the new version.
You need to ensure that the engineering change takes affect at the end of the month.
Solution:
1.) Create an activity for the new process step and add it to the existing production flow. Set the expiration date to the end of the month
2.) Create a Kanban rule that incorporates the new activity with an effective date of end of the month
3.) Edit the existing Kanban rule. Set the expiration date to the end of the month.
4.) Activate the new production flow
Does the solution meet the goal?
- A. Yes
- B. No
Answer: B
Explanation:
Section: Create and manage production and lean orders
Explanation
NEW QUESTION 25
A manufacturer produces HDMI cables. Typically, the item is manufactured.
The manufacturer will occasionally buy unbranded HDMI cables from a vendor in order to keep up with demand. The company must use the same item number whether they make or buy the item.
What should you do?
- A. Select route type as vendor on the route operation when the item is to be purchased.
- B. In default order settings, select Production for the default order type
- C. Create a new vendor resource when the item is to be purchased
- D. In default order settings, select Purchase for the default order type
Answer: A
NEW QUESTION 26
A company plans to account for indirect costs related to materials used to manufacture products.
The items used to manufacture products have surcharge rates that depend on the type of product being used.
You need to set up the costing sheet to include surcharges for specific items.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation:
NEW QUESTION 27
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?
- A. Navigate to the resource group. Change the calendar to closed on the resource group.
- B. Navigate to the calendar used for production and close the next two days.
- C. Navigate to the resource. Change the calendar to closed on the resource.
- D. Navigate to the resource and select Calendar deviations. Set the calendar to closed for the next two days.
Answer: D
NEW QUESTION 28
A company implements Dynamics 365 Finance and Operations.
You need to ensure that cost roll-ups and sales price calculations are configured for the scenario. Which options should you use? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.
Answer:
Explanation:
Explanation
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/bom-calculations
NEW QUESTION 29
......
How much Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing Exam Cost
The price of the Microsoft Mobility and Devices Fundamentals exam is USD 165, for more information related to the exam price please visit Microsoft Training website as prices of Microsoft exams fees get varied country wise.
How to book the Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing Exam
These are the following steps for registering for the Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing exam.
- Step 1: Visit Microsoft Learning and search for Microsoft MB-320: Microsoft Dynamics 365 Supply Chain Management, Manufacturing.
- Step 2: Sign up/log in to the Pearson VUE account
- Step 3: Select a local center based on your country, date, time, and confirm with a payment method.
MB-320 EXAM DUMPS WITH GUARANTEED SUCCESS: https://www.lead2passed.com/Microsoft/MB-320-practice-exam-dumps.html
Best Quality Microsoft MB-320 Exam Questions: https://drive.google.com/open?id=1sEGbq3tIV_gNBBNBqGK8jK1MkPXeqGTD